Compton High School Construction Update 


Media Release

Drive by the corner of Alondra Boulevard and S. Acacia Avenue in Compton, and you’ll see the construction site for the new Compton High School, scheduled to open in 2025. With nearly 150 people working on site daily, you’ll see new features being built every day. The school buildings are rising quickly, forming what will be the latest and most-advanced high school in the state of California.

Some of the current construction elements completed over the last several weeks include the structural steel added on the main academic building. In addition, crews poured concrete decks on the main parts of the second floor, the roof, and for the slab on the ground. Ongoing structural steel framing is being performed on the new gymnasium building, while preliminary site work is performed for the pool and performing arts center.

Compton Construction

 

Paving of the parking lot on Acacia has started, with gutters and curbs going in. That lot is needed as the construction crews will swell to almost 300 people working onsite daily by next spring.